Hartley Homes Framing

On March 20 the Building materials arrived at 10:00 AM, slightly behind schedule.  Acoustic seal and sill gaskets were placed on top of the footing wall to create an air tight seal between the footing wall and the bottom plate of the wall.  At the end of the day two walls were standing and by the end of today all 4 walls are in place.  Wall sheeting and interiors walls are planned for Wednesday and Thursday morning.  Roof trusses are scheduled to arrive on Thursday.