Hartley Homes Framing

T-Bracing in the roof trusses was completed on March 28.  Windows arrived the morning of March 29 and were installed the same day.  Roof shingles arrived Thursday March 30 and were installed the same day.  Plumbers arrived at 8:00 AM on Friday March 31 to install water supply and drain lines.  The wall insulation and vapor barrier behind the tub was installed and the tub arrived about 11:00 AM.  Ready for plumbing inspection at on Monday.