Back Framing, Insulation & Boarding

Great progress since the last post.  The final framing inspection was completed and passed by the District of Summerland on April 13.  The bulkheads/valance for the ducting was completed on April 14, Insulation was completed on April 17 and inspected on April 18.  The drywall was also loaded into the house on April 18. The boarding crew started early on the morning of April 19 and will be done by the end of the day today, the drywall filling and finishing should be ready for paint by May 1st.