Drywall finishing was completed on schedule, Exterior siding started today and is expected to be finished early next week. The prime coat of paint and first finish coat of paint will be completed on Friday April 28. Interior doors and trim will be delivered on Monday May 1st and the finishing of the trim will be completed May 3rd followed by paint of the trim on May 4 and 5 with the final coat of paint on the walls to be done by end of Day May 8.