Tuesday March 14, more mud and more back-filling. The plumbers arrived on time and installed the underground lines for sewer and water, great work between the plumbers and construction crew to place the gravel and sand and get it all packed into place, DOS inspection scheduled for 10:00 AM on Wednesday morning.