Wednesday March 15, the underground plumbing was passed by DOS at 10:30 this AM.  The position of the underground electrical cable under the slab was finalized just prior to lunch and temporary power was completed with the installation of a breaker in the main electrical box inside the rental house.
On Thursday we will complete the radon rock, slab seal and steel reinforcing bar for the slab, we expect inspection about lunch time, the concrete slab is scheduled for Friday Morning at 8:00 AM